Survey Work & Tree Removal

-A A +A

Harwinton was notified by Eversource that there will be work done between 7:00 am and 7:00 pm, Monday through Saturday for the following:

Week of April 24, 2017:

HARWINTON

Civil Construction – Crews continue to perform civil construction at Campville Substation on Wildcat Hill Road.

FOUNDATIONS AND STRUCTURES – Crews will be installing new foundations and transmission structures in the vicinity of Wildcat Hill Road.

TRANSMISSION LINE WORK -- Crews will be installing overhead lines in the vicinity of Valley Road.

If you have any questions, please contact First Selectman Michael Criss at (860) 485-9051.